Construction Schedule

Information will be updated as received

Will include:

Pre-demolition information, demolition information, traffic changes, noise, site safety etc.


Phase I Schedule

Phase I decommissioning (June 1, 2022):

  • Impacted courts - 1200, 900 and half of 1100 courts
    • 1115 - 1130 will be decommissioned
    • 900 and 1200 laundry rooms will be decommissioned
    • 1219 Children's Library will be relocated
  • Move-out of the affected courts will need to be completed by May 31, 2022
  • Internal decommissioning of vacant units will begin prior to June 2022
  • Resource fair to be held in early 2022

Phase II and III

Phase II

Planning for 2024:

  • Impacted courts - 800, 1000, remaining 1100 courts

Phase III

Planning for 2025/2026:

  • Impacted courts - 100 through 700 courts