Construction Schedule

Information will be updated as received

Will include:

Pre-demolition information, demolition information, traffic changes, noise, site safety etc.


Phase II: 2024 decommission TBD - information will be updated as it becomes available


Phase I Schedule

Phase I decommissioning (June 1, 2022): COMPLETE

Phase II

Phase II decommissioning (June 1, 2024)

  • Impacted courts:
    • 601 - 607
    • 1015 - 1019
    • Remaining 900 and 1100
  • Move-out of the affected courts will need to be completed by May 31, 2024
  • Decommissioning of vacant units will begin June 2024
  • Townhall to be held in early January 2024

Phase III

Phase III

Planning for 2026:

  • Impacted courts - all remaining courts